Dubai Building Approval Costs 2025: Complete Pricing Breakdown
Complete breakdown of Dubai building approval costs 2025. All fees for DM, DCD, consultants, and permits. Real examples for villas, restaurants, offices with exact pricing (AED 15K-150K).
Last Updated: December 2025 | Reading Time: 12 minutes
Understanding the true cost of building approvals in Dubai is crucial for budgeting any construction or renovation project. This comprehensive guide breaks down every cost component for 2025, from government fees to consultant charges, with real examples for villas, restaurants, offices, and commercial projects.
Quick Cost Overview 2025
Complete Approval Costs (All-Inclusive):
| Project Type | Total Cost Range |
|---|---|
| Villa Renovation (Minor) | AED 18,000 - 30,000 |
| Villa Extension + Pool | AED 35,000 - 50,000 |
| Restaurant (Small) | AED 45,000 - 70,000 |
| Restaurant (Large/Mall) | AED 65,000 - 95,000 |
| Office Fitout (Small) | AED 25,000 - 40,000 |
| Office Fitout (Large) | AED 45,000 - 75,000 |
| Retail Store (Mall) | AED 35,000 - 60,000 |
| Warehouse/Industrial | AED 40,000 - 80,000 |
| New Villa Construction | AED 80,000 - 150,000 |
These are approval costs only - construction costs are separate
Understanding Cost Components
The Three Main Cost Categories:
1. Professional Consultant Fees (60-70% of total)
- Architect (registered with DM)
- Structural engineer
- MEP (Mechanical, Electrical, Plumbing) engineer
- Civil Defence consultant
- Project management/coordination
2. Government Authority Fees (15-25% of total)
- Dubai Municipality building permit
- Dubai Municipality inspections
- Civil Defence approval fees
- Community/developer NOC fees
- Trade license fees (DED)
3. Additional Costs (10-20% of total)
- Fire safety systems and installation
- Kitchen suppression systems (F&B)
- Document translation (Arabic)
- Expedited processing fees (if needed)
- Re-submission fees (if applicable)
Detailed Cost Breakdown by Authority
Dubai Municipality Fees
Building Permit Fees (Based on Project Value):
DM calculates permit fees as percentage of construction value:
- 2.5% - 3.5% of declared construction cost
- Minimum: AED 2,000
- Maximum: No limit (percentage-based)
Example Calculations:
- AED 200,000 fitout → AED 6,000 permit fee
- AED 500,000 renovation → AED 15,000 permit fee
- AED 1,000,000 construction → AED 30,000 permit fee
Inspection Fees:
- Initial inspection: AED 500 - 1,000
- Foundation inspection: AED 500 (if applicable)
- Structural inspection: AED 500 - 1,000
- MEP inspection: AED 500 - 1,000
- Final inspection: AED 500 - 1,000
- Re-inspection (if failed): AED 500 per visit
Completion Certificate:
- Residential: AED 2,000 - 5,000
- Commercial: AED 3,000 - 8,000
Food License (F&B Projects):
- Application fee: AED 1,000 - 3,000
- Health inspection: AED 500 - 1,000
- Annual renewal: AED 1,000 - 2,500
Civil Defence Fees
Fire Safety Approval:
- Small projects (< 100 sqm): AED 500 - 1,000
- Medium projects (100-500 sqm): AED 1,000 - 2,000
- Large projects (> 500 sqm): AED 2,000 - 5,000
- Restaurant with kitchen: +AED 1,000 - 2,000
Inspection Fees:
- Initial inspection: AED 300 - 800
- Re-inspection: AED 500 - 1,000
Developer/Community NOC Fees
Emaar (Emirates Hills, Arabian Ranches, etc.):
- NOC application: AED 1,000 - 5,000
- Design review: Included
- Fitout deposit (refundable): AED 10,000 - 50,000
- Timeline: 2-4 weeks
Nakheel (Palm Jumeirah, Gardens, etc.):
- NOC application: AED 1,500 - 4,000
- Technical review: AED 500 - 1,000
- Timeline: 2-3 weeks
Mall Management Fees:
- Design approval: AED 2,000 - 5,000
- Fitout supervision: 2-3% of fitout cost
- Access card/permit: AED 500 - 1,000
- Signage approval: AED 1,000 - 3,000
Dubai Economy Department (DED)
Trade License (Mainland):
- Restaurant/F&B: AED 15,000 - 25,000/year
- Office activities: AED 15,000 - 20,000/year
- Retail: AED 15,000 - 22,000/year
- Industrial: AED 18,000 - 30,000/year
Free Zone License (DMCC, JAFZA, etc.):
- Generally 20-30% cheaper than mainland
- AED 10,000 - 20,000/year depending on zone
Professional Consultant Fees 2025
Architect Fees
Residential Projects:
- Villa renovation: AED 12,000 - 20,000
- Villa extension: AED 15,000 - 28,000
- New villa: AED 35,000 - 60,000
- Apartment fitout: AED 8,000 - 15,000
Commercial Projects:
- Small restaurant (< 150 sqm): AED 15,000 - 22,000
- Large restaurant (> 150 sqm): AED 22,000 - 35,000
- Office fitout (small): AED 12,000 - 20,000
- Office fitout (large): AED 20,000 - 35,000
- Retail store: AED 15,000 - 28,000
What's Included:
- Site survey and measurements
- Architectural design and drawings
- All floor plans, elevations, sections
- 3D renderings (usually 2-3 views)
- Coordination with engineers
- DM submission and follow-up
- Addressing DM comments (up to 2 revisions)
- Stamped approved drawings
Structural Engineer Fees
When Required:
- Any structural modifications
- Villa extensions or additions
- Removing or adding walls
- New construction
- Roof additions
- Swimming pools
Fee Structure:
- Villa renovation: AED 8,000 - 15,000
- Villa extension: AED 12,000 - 20,000
- New construction: AED 25,000 - 50,000
- Swimming pool: AED 4,000 - 8,000
Deliverables:
- Structural assessment
- Foundation design
- Structural calculations
- Reinforcement drawings
- Material specifications
- Engineer's stamp and certification
MEP Engineer Fees
When Required:
- Major HVAC changes
- Complete electrical rewiring
- New plumbing systems
- Commercial kitchens
- All F&B projects
- Large office fitouts
Fee Structure:
- Basic MEP coordination: AED 6,000 - 10,000
- Complete MEP design: AED 10,000 - 18,000
- Restaurant MEP: AED 12,000 - 22,000
- Large commercial: AED 18,000 - 35,000
Deliverables:
- HVAC layout and load calculations
- Electrical layout and panel schedules
- Plumbing and drainage plans
- Fire protection integration
- Energy efficiency compliance
- Stamped drawings
Civil Defence Consultant Fees
Fee Structure:
- Small commercial: AED 6,000 - 10,000
- Restaurant: AED 8,000 - 15,000
- Large commercial: AED 12,000 - 20,000
- Complex projects: AED 18,000 - 30,000
What's Included:
- Fire safety system design
- All DCD drawings and documentation
- Kitchen suppression system design (F&B)
- DCD submission and follow-up
- Inspection coordination
- Certificate collection
Project Management/Coordination
Optional but Recommended:
- Small projects: AED 5,000 - 10,000
- Medium projects: AED 10,000 - 18,000
- Large projects: AED 18,000 - 35,000
Services Provided:
- Coordinate all consultants
- Manage submission timeline
- Track all approvals
- Liaise with authorities
- Handle resubmissions
- Update client regularly
- Ensure nothing is missed
Fire Safety System Costs
Fire Alarm Systems
Small Installation (< 100 sqm):
- 3-5 smoke detectors
- 1-2 manual call points
- Control panel
- Alarm sounder
- Cost: AED 8,000 - 12,000
Medium Installation (100-500 sqm):
- 10-20 smoke detectors
- 3-5 manual call points
- Addressable control panel
- Multiple sounders
- Cost: AED 12,000 - 22,000
Large Installation (> 500 sqm):
- 20+ smoke detectors
- Heat detectors (where needed)
- Networked control panels
- Voice evacuation system
- Cost: AED 22,000 - 45,000
Kitchen Suppression Systems (F&B)
System Cost by Kitchen Size:
Small Kitchen (20-40 sqm):
- 4-6 nozzles
- Single tank
- Basic gas shut-off
- Cost: AED 15,000 - 22,000
Medium Kitchen (40-80 sqm):
- 6-10 nozzles
- Standard system
- Complete shut-off integration
- Cost: AED 22,000 - 30,000
Large Kitchen (80+ sqm):
- 10+ nozzles
- Multiple tanks or large capacity
- Full integration
- Cost: AED 30,000 - 45,000
Popular Brands:
- Ansul R-102: Industry standard
- Kidde: Reliable alternative
- Pyro-Chem: Premium option
Maintenance Costs:
- Semi-annual inspection: AED 800 - 1,200
- Annual full service: AED 1,500 - 2,500
- Agent replacement (12 years): AED 3,000 - 5,000
Emergency Lighting Systems
Basic System:
- Exit signs (LED)
- Emergency lights
- Battery backup
- Cost: AED 3,000 - 5,000
Standard System:
- Multiple exit signs
- Comprehensive emergency lighting
- Central battery system
- Cost: AED 5,000 - 10,000
Advanced System:
- Full path illumination
- Addressable system
- Remote monitoring
- Cost: AED 10,000 - 20,000
Fire Extinguishers
Cost per Unit:
- 6kg ABC: AED 200 - 300
- 9kg ABC: AED 300 - 400
- 6kg K-class (kitchen): AED 400 - 600
- CO2 extinguisher: AED 350 - 500
- Installation: AED 50 - 100/unit
Typical Requirements:
- Small office: 2-3 units = AED 800 - 1,200
- Restaurant: 5-8 units = AED 2,000 - 3,500
- Large commercial: 10+ units = AED 3,500 - 6,000
Real Project Examples with Complete Costs
Example 1: Villa Renovation (The Springs)
Project Details:
- Location: The Springs (Emaar)
- Scope: Kitchen extension + guest bedroom
- Area: 60 sqm addition
- Construction value: AED 350,000
Complete Cost Breakdown:
PROFESSIONAL FEES:
Architect AED 16,000
Structural Engineer AED 12,000
MEP Consultant AED 8,000
GOVERNMENT & DEVELOPER:
Emaar NOC AED 2,500
DM Building Permit AED 10,500
DM Inspections (3) AED 1,500
Completion Certificate AED 3,000
ADDITIONAL:
Document Translation AED 800
Miscellaneous AED 1,200
─────────────────────────────────────────
TOTAL APPROVAL COST AED 55,500
Construction (separate): AED 350,000
─────────────────────────────────────────
PROJECT TOTAL: AED 405,500
Timeline: 6-8 weeks for approvals
Example 2: New Restaurant (Dubai Marina Mall)
Project Details:
- Location: Marina Mall
- Type: Casual dining restaurant
- Area: 180 sqm (120 sqm dining + 60 sqm kitchen)
- Seating: 65 guests
- Construction value: AED 800,000
Complete Cost Breakdown:
PROFESSIONAL FEES:
Architect (F&B specialist) AED 25,000
MEP Engineer AED 15,000
Civil Defence Consultant AED 12,000
Project Management AED 10,000
GOVERNMENT FEES:
DM Building Permit AED 24,000
DM Food License AED 2,500
DM Health Inspection AED 1,000
Civil Defence Approval AED 2,500
Trade License (DED) AED 18,000
MALL MANAGEMENT:
Design Approval AED 3,000
Fitout Supervision (2.5%) AED 20,000
Access Permits AED 1,000
Signage Approval AED 2,000
FIRE SAFETY SYSTEMS:
Fire Alarm System AED 15,000
Kitchen Suppression (Ansul) AED 26,000
Emergency Lighting AED 6,000
Fire Extinguishers (7) AED 2,500
ADDITIONAL:
Arabic Translation AED 1,200
Fast-Track Processing AED 4,000
Miscellaneous AED 2,300
─────────────────────────────────────────
TOTAL APPROVAL COST AED 193,000
Kitchen Equipment: AED 250,000
Furniture & Finishes: AED 300,000
Fitout Construction: AED 800,000
─────────────────────────────────────────
PROJECT TOTAL: AED 1,543,000
Timeline: 12-16 weeks for approvals + fitout
Example 3: Office Fitout (Business Bay)
Project Details:
- Location: Business Bay (mainland)
- Type: Open-plan office with meeting rooms
- Area: 350 sqm
- Occupancy: 40 workstations
- Construction value: AED 450,000
Complete Cost Breakdown:
PROFESSIONAL FEES:
Architect AED 18,000
MEP Consultant AED 10,000
Civil Defence Consultant AED 8,000
GOVERNMENT FEES:
DM Building Permit AED 13,500
DM Inspections (2) AED 1,000
Civil Defence Approval AED 1,500
Completion Certificate AED 3,500
FIRE SAFETY SYSTEMS:
Fire Alarm System AED 16,000
Emergency Lighting AED 7,000
Fire Extinguishers (6) AED 1,800
ADDITIONAL:
Document Translation AED 800
Expedited Processing AED 3,000
Miscellaneous AED 1,400
─────────────────────────────────────────
TOTAL APPROVAL COST AED 85,500
Fitout Construction: AED 450,000
Furniture & IT: AED 180,000
─────────────────────────────────────────
PROJECT TOTAL: AED 715,500
Timeline: 8-10 weeks for approvals
Example 4: Retail Store (Dubai Mall)
Project Details:
- Location: Dubai Mall
- Type: Fashion retail
- Area: 200 sqm
- Construction value: AED 600,000
Complete Cost Breakdown:
PROFESSIONAL FEES:
Architect (Retail specialist) AED 20,000
MEP Consultant AED 9,000
Civil Defence Consultant AED 8,000
Project Coordination AED 8,000
GOVERNMENT FEES:
DM Building Permit AED 18,000
DM Inspections AED 1,500
Civil Defence Approval AED 1,800
EMAAR MALL FEES:
Design Approval AED 4,000
Fitout Supervision (3%) AED 18,000
Access & Security AED 1,500
Signage Package AED 3,000
FIRE SAFETY:
Fire Alarm (coordinated) AED 12,000
Emergency Lighting AED 5,500
Fire Extinguishers AED 1,500
ADDITIONAL:
Translation & Documents AED 1,000
Miscellaneous AED 1,700
─────────────────────────────────────────
TOTAL APPROVAL COST AED 114,500
Fitout Construction: AED 600,000
Fixtures & Displays: AED 120,000
─────────────────────────────────────────
PROJECT TOTAL: AED 834,500
Timeline: 10-14 weeks for approvals
Cost-Saving Strategies
1. Bundle Services with Single Provider
Instead of:
- Architect: AED 18,000
- Structural: AED 12,000
- MEP: AED 10,000
- DCD: AED 8,000
- Total: AED 48,000
Bundled Package:
- Complete approval service: AED 38,000 - 42,000
- Savings: AED 6,000 - 10,000
2. Avoid Resubmissions
Each resubmission costs:
- Time: 1-2 weeks delay
- Fees: AED 1,000 - 3,000 per resubmission
- Holding costs: Construction delays
Solution: Use experienced consultants who get it right first time (95%+ approval rate)
3. Plan Realistic Construction Value
Don't over-declare construction value:
- DM permit is 2.5-3.5% of declared value
- AED 100,000 over-declaration = AED 3,000 extra in fees
- Work with consultants to determine realistic value
4. Coordinate Approvals in Parallel
Run processes simultaneously:
- DM + DCD applications together
- Developer NOC while design finalizes
- System procurement during approval review
Time saved: 2-4 weeks Cost saved: Reduced holding costs
5. Choose Right Fire Safety Systems
Don't over-specify:
- Use standard approved systems (not premium)
- Ansul basic system vs. premium = AED 8,000 saved
- Standard fire alarm vs. addressable = AED 5,000 saved
- Only upgrade if truly required
6. Skip Unnecessary Fast-Track
Fast-track fees: AED 3,000 - 5,000
Only worth it if:
- You're genuinely late on timeline
- Lease/opening date can't move
- Cost of delay exceeds fast-track fee
For most projects, standard timeline is fine.
Hidden Costs to Watch For
1. Re-inspection Fees
If you fail inspection:
- AED 500 - 1,000 per re-inspection
- 1-2 week delay
- Possible construction corrections: AED 5,000 - 20,000
Prevention: Proper consultant + contractor coordination
2. Design Changes Mid-Approval
Changing plans after submission:
- Resubmission fees: AED 2,000 - 5,000
- Consultant revision fees: AED 3,000 - 8,000
- Timeline delay: 2-3 weeks
Prevention: Finalize design before submission
3. Mall Fitout Supervision Fees
Mall charges 2-3% of fitout cost:
- AED 500,000 fitout = AED 12,500 - 15,000 mall fee
- Often overlooked in initial budgets
- Non-negotiable
Planning: Always factor 3% of fitout cost for mall projects
4. System Maintenance Contracts
First year after opening:
- Kitchen suppression: AED 2,000 - 3,000/year
- Fire alarm: AED 1,500 - 2,500/year
- Emergency lighting: AED 800 - 1,200/year
Planning: Budget AED 4,000 - 7,000/year for ongoing compliance
5. Late Discovery of Requirements
Finding out mid-construction you need:
- Structural approval (not budgeted): AED 12,000
- Additional DCD systems: AED 15,000
- Developer NOC (forgot): AED 3,000
Prevention: Comprehensive initial assessment
Cost Comparison: DIY vs Professional Service
DIY Approach (Attempting Yourself)
Apparent Savings:
- No project management fee: AED 10,000 saved
- No coordination fee: AED 5,000 saved
- Total apparent savings: AED 15,000
Hidden Costs:
- Time spent (40-60 hours): Your time value
- Resubmissions (likely 2-3): AED 6,000 - 9,000
- Missed requirements: AED 10,000 - 30,000
- Timeline delays (6-8 weeks): Holding costs
- Stress and mistakes: Priceless
Actual Result: Usually costs MORE and takes 2x longer
Professional Service
Investment:
- Complete approval service: AED 35,000 - 65,000
- Timeline: 6-12 weeks (predictable)
- Success rate: 95%+ first-time approval
Benefits:
- Single point of contact
- Nothing missed
- Predictable timeline and cost
- Peace of mind
- Focus on your business
ROI: Saves 4-8 weeks and AED 10,000 - 40,000 in hidden costs
Payment Structure & Timeline
Typical Payment Schedule
For Professional Services:
Milestone 1: Engagement (30%)
- Upon signing agreement
- Initiates design work
Milestone 2: Submission (40%)
- When documents submitted to authorities
- Design complete and approved by you
Milestone 3: Approval (30%)
- When all approvals received
- Stamped drawings collected
Example for AED 50,000 Project:
- Engagement: AED 15,000
- Submission: AED 20,000
- Approval: AED 15,000
Government Fees Payment
Paid directly to authorities:
- DM fees: At submission time
- DCD fees: At application
- Developer NOC: At application
- Trade license: Annual upfront
System Installation Payment
Paid to specialized contractors:
- 50% upon order/contract
- 50% upon installation completion
FAQ: Dubai Building Approval Costs
How much does it cost to get building approval in Dubai?
Total cost range: AED 15,000 - 150,000
Depends on:
- Project type (residential vs commercial)
- Project size (sqm)
- Complexity (structural changes, F&B, etc.)
- Location (community requirements, mall fees)
Quick estimates:
- Simple villa renovation: AED 18,000 - 30,000
- Restaurant: AED 45,000 - 95,000
- Office fitout: AED 25,000 - 75,000
- New construction: AED 80,000 - 150,000
What percentage of construction cost is the building permit?
Dubai Municipality charges 2.5-3.5% of declared construction value for building permits.
Examples:
- AED 300,000 fitout → AED 9,000 permit
- AED 500,000 renovation → AED 15,000 permit
- AED 1,000,000 construction → AED 30,000 permit
This is just the permit - total approval costs are higher when including consultants and systems.
Can I reduce approval costs by doing some work myself?
No, not recommended. Dubai requires:
- DM-registered architects (can't use unlicensed)
- Certified engineers (must be licensed)
- Approved fire safety consultants
- Certified system installers
Attempting to cut corners results in:
- Rejected applications
- Higher costs from mistakes
- Significant delays
- Possible legal issues
Better approach: Get competitive quotes from 2-3 qualified firms.
Are approval costs tax-deductible in UAE?
Yes, for businesses:
- Professional fees: Fully deductible
- Government fees: Deductible
- Fire safety systems: Capital expenditure (depreciable)
For personal residences:
- Not applicable (UAE has no personal income tax)
- May add to property value for future sale
How long do approvals remain valid?
Once approved:
- Building permit: Valid 12 months from issuance
- Civil Defence approval: Valid until completion
- Trade license: Annual renewal required
If permit expires before construction completes:
- Extension request: AED 1,000 - 3,000
- Must show progress
- Maximum 1-2 extensions typically
What happens if I start construction before approval?
Serious consequences:
- Immediate stop-work order
- Fines: AED 50,000 - 500,000
- Forced demolition at your expense
- Cannot obtain completion certificate
- Legal liability issues
- Difficulty selling property later
Always wait for approvals before starting.
Get Accurate Quote for Your Project
Gravity Engineering provides transparent, all-inclusive approval service pricing with no hidden fees.
Our Service Includes:
- Complete feasibility assessment
- All consultant fees (architecture, engineering, DCD)
- All government submissions and follow-up
- Fire safety system coordination
- Project management throughout
- Guaranteed approval or money back
Transparent Pricing:
- Fixed-price quotes (no surprises)
- Itemized breakdown provided
- All revisions included (up to 3 rounds)
- Payment milestones tied to progress
Get Your Exact Quote:
- 📞 Call: +971 52 244 8485
- 💬 WhatsApp: Instant quote
- 🔗 Cost Calculator
Free Cost Estimate: Share your project details - receive detailed quote within 24 hours.
About This Guide: Pricing compiled by Gravity Engineering based on 200+ completed projects across Dubai in 2024-2025. All costs verified and current as of December 2025.